Write the formula, then the number.

On exam morning, put these seven on the whiteboard before question one.

BAC
$200,000
EV
$80,000
AC
$100,000
PV
$90,000

The sheet

  • CPIEV / AC
  • SPIEV / PV
  • CVEV − AC
  • SVEV − PV
  • EAC if the rate continuesBAC / CPI
  • EAC if the overrun was one-timeAC + (BAC − EV)
  • TCPI against the original budget(BAC − EV) / (BAC − AC)
  • VACBAC − EAC. Negative means you expect to finish over budget.

Under 1 is unfavorable for CPI and SPI. Contingency is inside the baseline for known risks. Management reserve is outside it, for unknown unknowns.